Charging the wrong appropriation can violate federal law. The PPBE Reform Commission counted 13 Antideficiency Act violations from FY2011 to FY2022 that used O&M money for software or system work.

The short version

  1. 1FMR Volume 2A, Chapter 1 gives new-obligation periods of 1 year for military personnel and O&M, 2 for RDT&E, 3 for procurement, and 5 for shipbuilding and military construction.
  2. 231 U.S.C. 1301(a) limits appropriations to their objects; 31 U.S.C. 1502(a) ties them to needs of their period of availability.
  3. 3The FMR sends equipment approved for production and intended for operational use or inventory to Procurement appropriations, not RDT&E.

"Colors of money" is the informal name for the separate kinds of appropriation that fund the Department of Defense (DoD): military personnel, operation and maintenance (O&M), procurement, research, development, test, and evaluation (RDT&E), and military construction. Each has its own purpose and period of availability. The governing rule is 31 U.S.C. 1301(a): appropriations "shall be applied only to the objects for which the appropriations were made," except as otherwise provided by law. The Commission on Planning, Programming, Budgeting, and Execution (PPBE) Reform used the term in its March 2024 final report and devoted a recommendation to it.

Expenses, investments, and the main appropriations

DoD's Financial Management Regulation (FMR), Volume 2A, Chapter 1, dated October 2008 and still the posted chapter as of April 2026, sorts every cost into expense or investment. Expenses are the costs to operate and maintain the organization, such as personal services, supplies, and utilities. Investments are costs that acquire or add to end items and benefit future periods.

The chapter then maps costs to appropriations. Costs budgeted in O&M and military personnel are expenses. Costs in procurement and military construction are investments. RDT&E, base realignment and closure, and family housing appropriations include both.

Division A of the Consolidated Appropriations Act, 2026, Public Law 119-75, approved February 3, 2026, shows the structure in law. Title I is Military Personnel, Title II Operation and Maintenance, Title III Procurement, and Title IV RDT&E, each split into accounts by Service, such as "Research, Development, Test and Evaluation, Army."

How long each color lasts

The FMR gives the normal life cycle of each appropriation. After its years for new obligations end, an appropriation is expired for five years, available only to adjust and pay existing obligations, and is then closed.

AppropriationYears for new obligationsClosed at end of year
Military personnel16
O&M16
RDT&E27
Procurement38
Shipbuilding and Conversion, Navy510 (15 in certain circumstances)
Military construction510

The 2026 act matches. Research, Development, Test and Evaluation, Army is available until September 30, 2027. Aircraft Procurement, Army runs to September 30, 2028, and Shipbuilding and Conversion, Navy to September 30, 2030. The military personnel and O&M paragraphs carry no date, and section 8003 says no appropriation in the act remains available beyond the current fiscal year unless the act expressly says so. Section 8004 adds that no more than 20 percent of one-year appropriations may be obligated in the last 2 months of the fiscal year.

The purpose statute

The Government Accountability Office (GAO) treatise Principles of Federal Appropriations Law, the Red Book, covers purpose in Chapter 3 of its fourth edition, 2017 revision. GAO says Congress first enacted the purpose statute in 1809. The statute prohibits charging authorized items to the wrong appropriation and unauthorized items to any appropriation.

GAO applies a three-step test. The expense must bear a logical relationship to the appropriation charged, must not be prohibited by law, and must not be provided for by another appropriation. Under the third step, a specific appropriation excludes a general one. In a 1959 case, the Navy could not use Shipbuilding and Conversion funds to dredge a river so submarines could leave a shipyard, because dredging rivers was the Army Corps of Engineers' funded function. When two appropriations are equally available, the agency picks one and must keep using it unless it tells Congress of a change for the next fiscal year, the rule GAO calls "pick and stick."

Moving money does not escape the rule. 31 U.S.C. 1532 permits a transfer between appropriation accounts only when authorized by law. GAO says an unauthorized transfer violates the purpose statute and, if the receiving account is then exceeded, the Antideficiency Act as well.

The bona fide needs rule

Time has its own rule. 31 U.S.C. 1502(a) makes a fixed-period appropriation available only for expenses properly incurred during its period of availability, or to complete contracts properly made within it. GAO's chapter on time remains the third edition's Volume I, dated January 2004. GAO traces section 1502(a) to 1870 and illustrates the rule with an agency that buys a truckload of pencils at year end with years of stock on hand: that purchase serves a future year's need, not the current one.

The rule applies to multiple-year money too, but across the whole period. GAO cites 68 Comp. Gen. 170 (1989), holding that the Defense Logistics Agency could use its fiscal year 1987 two-year research and development appropriation for a need that arose in fiscal year 1988.

Why research money cannot simply buy production

The FMR's RDT&E criteria draw the line. RDT&E pays for development and test work, including end items, equipment, and materials required for development and for developmental and operational testing. When there is doubt, the FMR resolves it in favor of RDT&E. But equipment approved for production and intended for operational use or inventory upon delivery is funded in Procurement. Product improvement within the current performance envelope goes to Procurement for systems in production, when no independent operational testing is needed, and to O&M for systems out of production.

The commission's Recommendation 11 describes the cost of these lines. It reports 13 Antideficiency Act violations from FY 2011 to FY 2022 involving O&M funds used instead of RDT&E or procurement for software or system obligations. It recounts the Air Force's Defense Enterprise Accounting and Management System (DEAMS), funded with a mix of RDT&E and O&M after Congress did not let more programs into the Budget Activity 8 software pilot in FY 2023. Recommendation 14 would let a program move limited money between RDT&E and procurement between Milestones B and C.

What to check

  • Which appropriation and fiscal year fund the work, and is that money still within its years for new obligations?
  • Is the item approved for production and intended for operational use or inventory? The FMR then points to Procurement.
  • Is there a more specific appropriation for the item, which the purpose statute would require instead?
  • Does the need belong to the period of availability of the money charged?
  • If funds moved between accounts, which law authorized the transfer?

Sources

  1. 1Principles of Federal Appropriations Law, Chapter 3, Availability of Appropriations: Purpose, Fourth Edition, 2017 Revision (GAO-17-797SP) · U.S. Government Accountability Office
  2. 2Principles of Federal Appropriations Law, Third Edition, Volume I (GAO-04-261SP), January 2004 · U.S. General Accounting Office
  3. 3United States Code, 2024 Edition, Title 31, Section 1301 - Application · U.S. Government Publishing Office
  4. 4United States Code, 2024 Edition, Title 31, Section 1502 - Balances available · U.S. Government Publishing Office
  5. 5United States Code, 2024 Edition, Title 31, Section 1532 - Withdrawal and credit · U.S. Government Publishing Office
  6. 6DoD 7000.14-R, Financial Management Regulation, Volume 2A, Chapter 1 (October 2008) · Office of the Under Secretary of Defense (Comptroller)
  7. 7Public Law 119-75, Consolidated Appropriations Act, 2026 · U.S. Government Publishing Office
  8. 8Defense Resourcing for the Future: Final Report · Commission on Planning, Programming, Budgeting, and Execution Reform, March 6, 2024

Where this shows up in our work

More on acquisition